The building had been unused for over 10 years and had suffered from neglect and vandalism. By employing modern methods and materials, the building now visually reflects its original appearance while offering modern facilities that meet current Building Regulation Standards. The area around the building was also improved to provide better access for disabled visitors.

  • Project Title: Floral Hall, Tunstall Park
  • Scheme Budget: £750,000
  • Project Period: 20 weeks
  • Procurement Strategy: Partnering (PPC 2000)
  • Role Undertaken on Project: Project Manager
  • Other Consultants: BBLB Architects
  • Client: Stoke-on-Trent City Council
  • Client Users: Tunstall Community Centre
  • Contractor: Carillion
  • Description of work: The refurbishment of a fire damaged park pavilion
    Project driver: To provide a new location for the Tunstall Community Centre